Highlands Community League
Revised 2026 Hall Construction Schedule

Due to the 100-year unprecedented rainfall experienced this summer our construction schedule has been delayed, and requires a revision. The good
news is that progress continues to be made and there are now visible signs of our new hall. The following is the revised schedule, subject to weather
and unforeseen circumstances:

1. The foundation has been poured and forms removed.

2. Week of Sept. 7, the plumbers and electricians will be installing the interior sub-floor piping as the final interior grade is installed and compacted.

3. Week of Sept. 14, Subtrades will be installing the exterior deep underground piping for the sanitary sewer and water lines, tying into the existing water and sanitary lines. They will also be installing piping around the perimeter to handle stormwater from the roof – this was unanticipated and new. This piping will now connect with Epcor stormwater piping on 113 ave.

4. Week of Sept. 21 and Sept. 28, the final grade around the building will be installed, bringing in black dirt to final grade and all concrete for the exterior including the new walkway out to 62 Street will be installed. The reason for this is so that the final concrete work is done before freeze-up.

5. The framing will be done once the concrete work is completed because framing can be done as the weather gets colder.

6. The site Superintendent said this afternoon that occupancy could still happen at the end of February or early March as originally planned.

7. Landscaping will happen in the spring.

 

We can’t wait to welcome you back into a brand-new space built for our community. Stay tuned for updates!

Hall is now closed for construction in 2026

Design for the New Hall

SOUTH EAST VIEW
SOUTH EAST VIEW

Rendering of the current Community Hall Design, for which detailed construction documents have been prepared.

Shopping Cart